BC Hydro

2020 Street Lighting Rate

Completed: 2021

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: June 4, 2021 @ 9:19 am
Decision and Order G-312-21 Decision and Order G-312-21 November 1, 2021

Arguments/Submissions

Title Document Description
BC Hydro Final Argument Final Argument May 6, 2021
BC Hydro Final Argument Erratum Final Argument Erratum May 10, 2021
BCSEA Final Argument Final Argument May 18, 2021
Kamloops Final Argument Final Argument May 18, 2021
ZoneII RPG Final Argument Final Argument May 20, 2021
Surrey Final Argument Final Argument May 20, 2021
Vernon Final Argument Final Argument May 20, 2021
CEC Final Argument Final Argument May 20, 2021
BCOAPO Final Argument Final Argument May 20, 2021
BC Hydro Reply Argument Reply Argument June 3, 2021

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
November 13, 2020 A-1 Letter dated November 13, 2020 - Appointing the Panel for the review of British Columbia Hydro and Power Authority 2020 Street Lighting Rate Application
November 30, 2020 A-2 Letter dated November 30, 2020 – BCUC Order G-302-20 establishing a regulatory timetable
January 14, 2021 A-3 Letter dated January 14, 2021 – BCUC Information Request No. 1 to BC Hydro
February 03, 2021 A-4 Letter dated February 3, 2021 – BCUC amending the Panel for the review of the Application
February 12, 2021 A-5 Letter dated February 12, 2021 – BCUC Order G-43-21 establishing a regulatory timetable
March 11, 2021 A-6 Letter dated March 11, 2021 – BCUC Information Request No. 2 to BC Hydro
April 22, 2021 A-7 Letter dated April 22, 2021 – BCUC Order G-119-21 establishing a further regulatory timetable
May 12, 2021 A-8 Letter dated May 12, 2021 – BCUC request for comments on Late Letter of Comment

B Exhibits - Applicant Documents

Date Title Document Description
November 13, 2020 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated November 11, 2020 Submitting 2020 Street Lighting Rate Application
December 23, 2020 B-2 Letter dated December 23, 2020 – BC Hydro submitting compliance with Order G-302-20 Directives 4, 5 and 7
January 20, 2021 B-3 Letter dated January 20, 2021 – BC Hydro submitting compliance with G-302-20 Directive 7
February 04, 2021 B-1-1 Letter dated February 4, 2021 – BC Hydro submitting errata to the Application
February 04, 2021 B-4 Letter dated February 4, 2021 – BC Hydro submitting response to BCUC Information Request No. 1
February 04, 2021 B-4-1 CONFIDENTIAL- Letter dated February 4, 2021 – BC Hydro submitting confidential response to BCUC Information Request No. 1
February 04, 2021 B-5 Letter dated February 4, 2021 – BC Hydro submitting response to Intervener Information Request No. 1
February 04, 2021 B-5-1 CONFIDENTIAL - Letter dated February 4, 2021 – BC Hydro submitting confidential response to Intervener Information Request No. 1
April 01, 2021 B-5-2 Letter dated April 1, 2021 – BC Hydro submitting revision to responses to Intervener Information Requests p MHPOABC 1.1A, 1.1B and 1.2G
April 01, 2021 B-6 Letter dated April 1, 2021 – BC Hydro submitting response to BCUC Information Request No. 2
April 01, 2021 B-7 Letter dated April 1, 2021 – BC Hydro submitting response to Intervener Information Requests No. 2
May 14, 2021 B-8 Letter dated May 14, 2021 – BC Hydro submitting response regarding Late Letter of Comment
June 03, 2021 B-1-2 Letter dated June 3, 2021 – BC Hydro submitting errata No. 2 to the Application

C Exhibits - Intervener Documents

BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) – Letter dated December 7, 2020 submitting request to intervene by William Andrews
KWADACHA NATION AND TSAY KEH DENE NATION, TOGETHER THE ZONE II RATEPAYERS GROUP (ZONE II RPG) – Letter dated December 11, 2020 submitting request to intervene by Jana Mclean
DISTRICT OF LILLOOET (LILLOOET)– Letter dated December 14, 2020 submitting request to intervene by Rory Card
CITY OF NORTH VANCOUVER (CONV) – Request to Intervene and Letter of Comment dated December 18, 2020 submitted by Douglas Pope, Director, Engineering Parks and Environment
CORPORATION OF THE VILLAGE OF ASHCROFT (ASHCROFT) – Request to Intervene and comment dated December 18, 2020 submitted by Mayor Barbara Roden
MANUFACTURED HOME PARK OWNERS ALLIANCE OF BC (MHPOABC)– Letter dated December 17, 2020 submitting request to intervene by Al Kemp
HILL, LARRY (HILL) – Letter dated December 21, 2020 submitting request to intervene
BRITISH COLUMBIA AGRICULTURE COUNCIL (BCAC) – Letter dated December 23, 2020 submitting request to intervene by Fred Weisberg, Weisberg Law Corporation
BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY (BCOAPO ET AL.) – Letter dated December 22, 2020 submitting request to intervene by Leigha Worth and Irina Mis
COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) - Letter dated December 22, 2020 Request to Intervene by Chris Weafer, Owen Bird Law Corporation
CITY OF SURREY (SURREY) – Letter dated December 22, 2020 submitting request to intervene by Hugh Campbell
CITY OF VERNON (VERNON) – Letter dated January 14, 2021 submitting request to intervene by James Yardley, Lidstone & Company
RESIDENTIAL CONSUMER INTERVENOR GROUP (RCIG) - Letter dated January 25, 2021 Request to Intervene by Lindsay Thompson, Midgard Consulting
CITY OF KAMLOOPS (KAMLOOPS) – Letter dated January 26, 2021 Request to Intervene by Jen Fretz, Director of Civic Operations


Date Title Document Description
December 07, 2020 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) – Letter dated December 7, 2020 submitting request to intervene by William Andrews
January 21, 2021 C1-2 Letter dated January 21, 2021 – BCSEA submitting Information Request No. 1 to BC Hydro
March 11, 2021 C1-3 Letter dated March 11, 2021 – BCSEA submitting Information Request No. 2 to BC Hydro
December 11, 2020 C2-1 KWADACHA NATION AND TSAY KEH DENE NATION, TOGETHER THE ZONE II RATEPAYERS GROUP (ZONE II RPG) – Letter dated December 11, 2020 submitting request to intervene by Jana Mclean
January 21, 2021 C2-2 Letter dated January 21, 2021 – ZoneII-RPG submitting Information Request No. 1 to BC Hydro
March 11, 2021 C2-3 Letter dated March 11, 2021 – ZoneII-RPG submitting Information Request No. 2 to BC Hydro
December 14, 2020 C3-1 DISTRICT OF LILLOOET (LILLOOET)– Letter dated December 14, 2020 submitting request to intervene by Rory Card
December 18, 2020 C4-1 CORPORATION OF THE VILLAGE OF ASHCROFT (ASHCROFT) – Request to Intervene and comment dated December 18, 2020 submitted by Mayor Barbara Roden
December 17, 2020 C5-1 MANUFACTURED HOME PARK OWNERS ALLIANCE OF BC (MHPOABC)– Letter dated December 17, 2020 submitting request to intervene by Al Kemp
January 21, 2021 C5-2 Letter dated January 21, 2021 – MHPOABC submitting Information Request No. 1 to BC Hydro
March 08, 2021 C5-3 Letter dated March 8, 2021 – MHPOABC submitting Information Request No. 2 to BC Hydro
December 21, 2020 C6-1 HILL, LARRY (HILL) – Letter dated December 21, 2020 submitting request to intervene
January 20, 2021 C6-2 Letter dated January 20, 2021 – Hill submitting Information Request No. 1 to BC Hydro
December 18, 2020 C7-1 CITY OF NORTH VANCOUVER (CONV) – Request to Intervene and Letter of Comment dated December 18, 2020 submitted by Douglas Pope, Director, Engineering Parks and Environment
January 21, 2021 C7-2 Letter dated January 21, 2021 – CoNV submitting Information Request No. 1 to BC Hydro
December 23, 2020 C8-1 BRITISH COLUMBIA AGRICULTURE COUNCIL (BCAC) – Letter dated December 23, 2020 submitting request to intervene by Fred Weisberg, Weisberg Law Corporation
January 21, 2021 C8-2 Letter dated January 21, 2021 – BCAC submitting Information Request No. 1 to BC Hydro
March 11, 2021 C8-3 Letter dated March 11, 2021 – BCAC submitting Information Request No. 2 to BC Hydro
December 22, 2020 C9-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY (BCOAPO ET AL.) – Letter dated December 22, 2020 submitting request to intervene by Leigha Worth and Irina Mis
January 21, 2021 C9-2 Letter dated January 21, 2021 – BCOAPO submitting Information Request No. 1 to BC Hydro
March 11, 2021 C9-3 Letter dated March 11, 2021 – BCOAPO submitting Information Request No. 2 to BC Hydro
December 22, 2020 C10-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) - Letter dated December 22, 2020 Request to Intervene by Chris Weafer, Owen Bird Law Corporation
January 21, 2021 C10-2 Letter dated January 21, 2021 – CEC submitting Information Request No. 1 to BC Hydro
March 11, 2021 C10-3 Letter dated March 11, 2021 – CEC submitting Information Request No. 2 to BC Hydro
December 22, 2020 C11-1 CITY OF SURREY (SURREY) – Letter dated December 22, 2020 submitting request to intervene by Hugh Campbell
January 21, 2021 C11-2 Letter dated January 21, 2021 – Surrey submitting Information Request No. 1 to BC Hydro
March 11, 2021 C11-3 Letter dated March 11, 2021 – Surrey submitting Information Request No. 2 to BC Hydro
January 14, 2021 C12-1 CITY OF VERNON (VERNON) – Letter dated January 14, 2021 submitting request to intervene by James Yardley, Lidstone & Company
March 11, 2021 C12-2 Letter dated March 11, 2021 – Vernon submitting Information Request No. 2 to BC Hydro
January 25, 2021 C13-1 RESIDENTIAL CONSUMER INTERVENOR GROUP (RCIG) - Letter dated January 25, 2021 Request to Intervene by Lindsay Thompson, Midgard Consulting
January 26, 2021 C14-1 CITY OF KAMLOOPS (KAMLOOPS) – Letter dated January 26, 2021 Request to Intervene by Jen Fretz, Director of Civic Operations

D Exhibits — Interested Party Documents

Date Title Document Description
December 01, 2020 D-1 YOUDEN, L. (YOUDEN) – Submission dated December 1, 2020 Request for Interested Party Status
December 01, 2020 D-1-1 YOUDEN – Letter of Comment dated December 1, 2020
December 09, 2020 D-6 ALOUETTE RIVER MOBILE HOME PARK (ALOUETTE RIVER-MHP) – Submission dated December 9, 2020 Request for Interested Party Status by Ann Hansson
December 09, 2020 D-6-1 ALOUETTE RIVER-MHP – Letter of Comment dated December 9, 2020
December 12, 2020 D-2 HURD, J. (HURD) – Submission dated December 12, 2020 Request for Interested Party Status
December 12, 2020 D-2-1 HURD – Letter of Comment dated December 12, 2020
December 14, 2020 D-5 CHRYSTAL RIVER COURT LTD. (CHRYSTAL RIVER) – Submission dated December 14, 2020 Request for Interested Party Status by John Nelson
December 14, 2020 D-4-1 BIFFERT - Letter of Comment dated December 14, 2020
December 14, 2020 D-3 FORTISBC INC. (FBC) – Submission dated December 14, 2020 Request for Interested Party Status by Diane Roy
December 16, 2020 D-4 BIFFERT, W. (BIFFERT) - Submission dated December 16, 2020 Request for Interested Party Status
December 17, 2020 D-7 MANUFACTURED HOME PARK OWNERS ALLIANCE OF BC (MHPOA-BC) - Submission dated December 17, 2020 Request for Interested Party Status by Al Kemp
December 18, 2020 D-8-1 BURNABY – Letter of Comment dated December 18, 2020
December 19, 2020 D-8 CITY OF BURNABY (BURNABY) - Submission dated December 19, 2020 Request for Interested Party Status by Doug Louie
December 21, 2020 D-9 REMOVED NOW EXHIBIT C6-1
December 21, 2020 D-10 CITY OF LANGLEY (LANGLEY) – Submission dated December 21, 2020 Request for Interested Party Status by Hirod Gill
December 21, 2020 D-10-1 LANGLEY – Letter of Comment dated December 21, 2020
December 22, 2020 D-11 ASSAF, RON (ASSAF) - Submission dated December 22, 2020 Request for Interested Party Status
December 30, 2020 D-12 REID, TRENT (REID) - Submission dated December 30, 2020 Request for Interested Party Status
March 02, 2021 D-13 VERRAN, STAN (VERRAN) - Submission dated March 2, 2020 Request for Interested Party Status
March 09, 2021 D-14 SOUTHERN INTERIOR LOCAL GOVERNMENT ASSOCIATION (SILGA) - Submission dated March 9, 2021 Request for Interested Party Status by Alison Slater
May 10, 2021 D-15 KELSEY, DAVID (KELSEY) - Submission dated May 10, 2021 Request for Interested Party Status
May 10, 2021 D-15-1 KELSEY – Letter of Comment dated May 10, 2021

E Exhibits - Letters of Comment

Date Title Document Description
October 21, 2020 E-1 British Columbia Cattlemen’s Association (BCCA) – Letter of Comment dated October 21, 2020
December 07, 2020 E-2 FEATHER, B. – Letter of Comment dated December 7, 2020
December 14, 2020 E-4 FUNK, D. – Letter of Comment dated December 14, 2020
December 18, 2020 E-6 CARIBOO REGIONAL DISTRICT AND MEMBER MUNICIPALITIES (CRD-MM) – Letter of Comment dated December 18, 2020 submitted by Lore Schick
December 18, 2020 E-7 CITY OF WILLIAMS LAKE (WILLIAMS LAKE) – Letter of Comment dated December 18, 2020 submitted by Mayor Walt Cobb
December 21, 2020 E-8 REMOVED NOW EXHIBIT C4-1
December 21, 2020 E-5 REMOVED NOW EXHIBIT D-4-1
December 21, 2020 E-3 REMOVED NOW EXHIBIT D-6-1
December 22, 2020 E-9 TOWNSHIP OF LANGLEY (TOWNSHIP OF LANGLEY) – Letter of Comment dated December 22, 2020 submitted by Roeland Zwagg
January 04, 2021 E-12 OAKES, C. MLA - Letter of Comment dated January 4, 2021
January 07, 2021 E-11 LAASS, V. – Letter of Comment dated January 7, 2021
January 07, 2021 E-10 Removed now Exhibit C7-1
January 11, 2021 E-13 DISTRICT OF CLEARWATER – Letter of Comment dated January 11, 2021 submitted by Merlin Blackwell
January 22, 2021 E-14 CITY OF ENDERBY - Letter of Comment dated January 22, 2021 submitted by Tate Bengtson, Chief Administrative Officer
January 28, 2021 E-15 NORTH COAST REGIONAL DISTRICTS -Letter of Comment dated January 28, 2021 submitted by Barry Pages, Chair
February 11, 2021 E-16 MUNICIPALITY OF NORTH COWICHAN -Letter of Comment dated February 11, 2021 submitted by Al Siebring, Mayor
February 23, 2021 E-17 CLUB MANAGER - Letter of Comment dated February 23, 2021 submitted on behalf of the Maple Bay Yacht Club
March 04, 2021 E-18 BEARDSLEY, J. – Letter of Comment dated March 4, 2021
March 17, 2021 E-19 CITY OF PRINCE GEORGE – Letter of Comment dated March 17, 2021 submitted by Mayor Lyn Hall
March 22, 2021 E-20 REGIONAL DISTRICT OF MOUNT WADDINGTON (RDMW) – Letter of Comment dated March 22, 2021 submitted by Andrew Hory, Chair
March 30, 2021 E-24 CORPORATION OF THE VILLAGE OF MCBRIDE (MCBRIDE) – Letter of Comment dated March 30, 2021 submitted by Chris Tupy, Chief Administrative Officer
April 01, 2021 E-21 DISTRICT OF LOGAN LAKE (LOGAN LAKE) – Letter of Comment dated April 1, 2021 submitted by Melisa Miles, Director of Corporate Affairs
April 05, 2021 E-22 BURNS LAKE – Letter of Comment dated April 5, 2021 submitted by Mayor Dolores Funk
April 07, 2021 E-25 VILLAGE OF PORT ALICE (PORT ALICE) – Letter of Comment dated April 7, 2021 submitted by Mayor Kevin Cameron
April 08, 2021 E-23 TOWN OF GOLDEN (GOLDEN) – Letter of Comment dated April 8, 2021 submitted by Mayor Ron Oszust
April 13, 2021 E-26 DISTRICT OF ELKFORD (ELKFORD) – Letter of Comment dated April 13, 2021 submitted by Mayor Dean McKerracher
April 15, 2021 E-29 VILLAGE OF HARRISON HOT SPRINGS (HARRISON) – Letter of Comment dated April 15, 2021 submitted by Mayor Leo Facio
April 15, 2021 E-30 VILLAGE OF MASETT (MASSET) – Letter of Comment dated April 15, 2021 submitted by Alan Smith, Chief Administrative Officer
April 21, 2021 E-31 CITY OF CAMPBELL RIVER (CAMPBELL RIVER) – Letter of Comment dated April 21, 2021 submitted by Mayor Andy Adams
April 23, 2021 E-28 VILLAGE OF CHASE (CHASE) – Letter of Comment dated April 23, 2021 submitted by Mayor Rod Crowe
April 27, 2021 E-27 NORTHERN ROCKIES REGIONAL MUNICIPALITY (NRRM) – Letter of Comment dated April 27, 2021 submitted by Mayor Gary Foster
April 30, 2021 E-32 DISTRICT OF KITIMAT (KITIMAT) – Letter of Comment dated April 30, 2021 submitted by Mayor Phil Germuth
May 05, 2021 E-34 THE DISTRICT OF NEW HAZELTON – Letter of Comment dated May 5, 2021 submitted by Gail Lowry (Mayor)
May 07, 2021 E-33 THOMPSON-NICOLA REGIONAL DISTRICT (TN-RD) – Letter of Comment dated May 7, 2021 submitted by Kenneth Gillis, Chair

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more