Creative Energy

Rates for the Mount Pleasant District Cooling System

Completed: 2022

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: May 24, 2022 @ 12:16 pm
Decision and G-242-22 Decision and Final Order August 22, 2022
G-1-23 Final Order varying G-242-22 January 4, 2023

Arguments/Submissions

Title Document Description
Creative Energy Final Argument Final Argument May 26, 2022
CEC Final Argument Final Argument June 9, 2022
Creative Energy Reply Argument Reply Argument June 16, 2022

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
February 05, 2021 A-1 Letter dated February 5, 2021 – Appointing the Panel for the review of the Creative Energy Application for Rates for the Mount Pleasant District Cooling System
February 18, 2021 A-2 Letter dated February 18, 2021 – BCUC Order G-46-21 issuing interim approvals
November 10, 2021 A-3 Letter dated November 10, 2021 - BCUC requesting comments from CEMP
December 02, 2021 A-4 Letter dated December 2, 2021 – BCUC Order G-352-21 establishing a regulatory timetable
January 31, 2022 A-5 Letter dated January 31, 2022 – BCUC Information Request No. 1 to CEMP
February 18, 2022 A-6 Letter dated February 18, 2022 – BCUC response to Creative Energy extension request
March 14, 2022 A-7 Letter dated March 14, 2022 – BCUC Order G-76-22 establishing a regulatory timetable and Reasons for Decision
April 01, 2022 A-8 Letter dated April 1, 2022 – BCUC Information Request No. 2 to CEMP
May 13, 2022 A-9 Letter dated May 13, 2022 – BCUC Order G-131-22 establishing an amended regulatory timetable with BCUC request for submissions
May 24, 2022 A-10 Letter dated May 24, 2022 – BCUC response to extension request

B Exhibits - Applicant Documents

Date Title Document Description
May 24, 2022 B-13 Letter dated May 24, 2022 – Creative Energy submitting extension request to file Written Final Argument
May 02, 2022 B-12 Letter dated May 2, 2022 – Creative Energy submitting responses to CEC Information Request No. 2
May 02, 2022 B-11 Letter dated May 2, 2022 – Creative Energy submitting responses to BCUC Information Request No. 2
March 21, 2022 B-10 Letter dated March 21st, 2022 – Creative Energy submitting revised Rates Model in compliance with G-76-22
March 01, 2022 B-9 Letter dated March 1, 2022 – Creative Energy submitting Evidentiary Update
February 25, 2022 B-8 Letter dated February 25 2022 – Creative Energy submitting response to CEC Information Request No. 1
February 25, 2022 B-7 Letter dated February 25, 2022 – Creative Energy submitting response to BCUC Information Request No. 1
February 17, 2022 B-6 Letter dated February 17, 2022 – Creative Energy submitting extension request to file responses to Information Request No. 1
January 07, 2022 B-5 Letter dated January 7, 2022 – Creative Energy submitting compliance with G-352-21 Directives 3, 4, 5 and 6 Notification
January 07, 2022 B-4 Letter dated January 7, 2022 – Creative Energy submitting Updated Rates Model compliance with G-352-21 Directive 7
November 22, 2021 B-3 Letter dated November 22, 2021 – Creative Energy response to BCUC request
October 14, 2021 B-2 Letter dated October 14, 2021 – Creative Energy submission regarding Evidentiary Update timing
February 01, 2021 B-1 CREATIVE ENERGY MOUNT PLEASANT LIMITED PARTNERSHIP (CREATIVE ENERGY) - Application for Rates for the Mount Pleasant District Cooling System dated February 1, 2021

C Exhibits - Intervener Documents

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more