June 14, 2023 |
B-1 |
BC HYDRO AND POWER AUTHORITY (BC HYDRO) – PUBLIC - Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application dated June 14, 2023 |
June 14, 2023 |
B-1-1 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix A |
June 14, 2023 |
B-1-2 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix B |
June 14, 2023 |
B-1-3 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C1 and C2 |
June 14, 2023 |
B-1-4 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 1 |
June 14, 2023 |
B-1-5 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 2 |
June 14, 2023 |
B-1-6 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 3 |
June 14, 2023 |
B-1-7 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 4 |
June 14, 2023 |
B-1-8 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 5 |
June 14, 2023 |
B-1-9 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 6 |
June 14, 2023 |
B-1-10 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 7 |
June 14, 2023 |
B-1-11 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 8 |
June 14, 2023 |
B-1-12 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 9 |
June 14, 2023 |
B-1-13 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 10 |
June 14, 2023 |
B-1-14 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C3 Part 11 |
June 14, 2023 |
B-1-15 |
PUBLIC – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C4 to C10 |
October 16, 2023 |
B-1-16 |
PUBLIC – Letter dated October 16, 2023 – BC Hydro submitting Errata No. 1 to the Application |
June 14, 2023 |
B-2 |
CONFIDENTIAL – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application |
June 14, 2023 |
B-2-1 |
CONFIDENTIAL – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix A |
June 14, 2023 |
B-2-2 |
CONFIDENTIAL – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix B |
October 16, 2023 |
B-2-2-1 |
CONFIDENTIAL – Letter dated October 16. 2023 – BC Hydro submitting Errata No. 1 to Confidential Application Appendix B |
June 14, 2023 |
B-2-3 |
CONFIDENTIAL – Letter dated June 14, 2023 – BC Hydro submitting Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project Application Appendix C |
October 16, 2023 |
B-2-3-1 |
CONFIDENTIAL – Letter dated October 16. 2023 – BC Hydro submitting Errata No. 1 to Confidential Application Appendix C |
October 16, 2023 |
B-2-4 |
CONFIDENTIAL – Letter dated October 16, 2023 – BC Hydro submitting Errata No. 1 to the Confidential Application |
July 31, 2023 |
B-3 |
Letter dated July 31, 2023 – BC Hydro submitting proof of public notice in compliance with Order G-189-23 |
October 17, 2023 |
B-4 |
PUBLIC – Letter dated October 17, 2023 – BC Hydro submitting redacted responses to BCUC Information Request No. 1 |
October 17, 2023 |
B-4-1 |
CONFIDENTIAL – Letter dated October 17, 2023 – BC Hydro submitting confidential responses to BCUC Information Request No. 1 |
October 17, 2023 |
B-5 |
CONFIDENTIAL – Letter dated October 17, 2023 – BC Hydro submitting confidential responses to BCUC Confidential Information Request No. 1 |
October 17, 2023 |
B-6 |
PUBLIC – Letter dated October 17, 2023 – BC Hydro submitting redacted responses to Interveners Information Requests No. 1 |
October 17, 2023 |
B-6-1 |
CONFIDENTIAL – Letter dated October 17, 2023 – BC Hydro submitting confidential responses to Interveners Information Requests No. 1
|
November 29, 2023 |
B-7 |
Letter dated November 29, 2023 – BC Hydro submitting extension request to file responses to BCOAPO Information Requests No. 2 |
December 07, 2023 |
B-8 |
PUBLIC – Letter dated December 7, 2023 – BC Hydro submitting responses to BCUC public Information Request No. 2 |
December 07, 2023 |
B-9 |
CONFIDENTIAL – Letter dated December 7, 2023 – BC Hydro submitting responses to BCUC Confidential Information Request No. 2 |
December 07, 2023 |
B-10 |
Letter dated December 7, 2023 – BC Hydro submitting responses to Interveners Information Requests No. 2 |
December 12, 2023 |
B-11 |
Letter dated December 12, 2023 – BC Hydro submitting Cost Estimate Update and request for adjournment |
December 14, 2023 |
B-12 |
Letter dated December 14, 2023 – BC Hydro submitting responses to BCOAPO Information Requests No. 2 |
January 25, 2024 |
B-13 |
Letter dated January 25, 2024 – BC Hydro submitting update on the status of project cost information in compliance with Order G-352-23 |
May 30, 2024 |
B-14 |
PUBLIC - Letter dated May 30, 2024 – BC Hydro submitting redacted update on the status of project cost information in compliance with Order G-25-24 |
May 30, 2024 |
B-14-1 |
CONFIDENTIAL - Letter dated May 30, 2024 – BC Hydro submitting confidential update on the status of project cost information in compliance with Order G-25-24 |
July 18, 2024 |
B-15 |
PUBLIC - Letter dated July 18, 2024 – BC Hydro submitting responses to BCUC and Intervener Information Requests No. 3 |
July 18, 2024 |
B-15-1 |
CONFIDENTIAL - Letter dated July 18, 2024 – BC Hydro submitting confidential responses to Intervener Information Requests No. 3 |
October 29, 2024 |
B-16 |
Letter dated October 29, 2024 – BC Hydro submitting update on the status of the Strathcona project cost estimate in compliance with Order G-163-24 |