BC Hydro

Non-Integrated Areas Planning Regulatory Framework

In Progress

BC Hydro proposes a regulatory framework for the review of resource planning in the Non-Integrated Areas.

Timetable

Subject Date
BC Hydro responses to BCUC and Intervener IR No. 1 Friday, April 26, 2024
Deadline for Letters of comment on the Proposal Thursday, May 16, 2024
BC Hydro to provide a reply, if any, to the Letters of comment Thursday, May 23, 2024
Further process TBD

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: March 20, 2024 @ 10:46 am

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
January 15, 2024 A-1 Letter dated January 15, 2024 – Appointing the Panel for the review of the BC Hydro Non-Integrated Areas Planning Regulatory Framework
January 25, 2024 A-2 Letter dated January 25, 2024 – BCUC Order G-23-24 establishing a regulatory timetable
February 29, 2024 A-3 Letter dated February 29, 2024 – BCUC Information Request No. 1 to BC Hydro
March 20, 2024 A-4 BCUC Order G-80-24 amending the regulatory timetable

B Exhibits - Applicant Documents

Date Title Document Description
December 15, 2023 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) - Non-Integrated Areas Planning Regulatory Framework Application dated December 15, 2023
February 09, 2024 B-2 PUBLIC - Letter dated February 9, 2024 – BC Hydro submitting evidentiary update and compliance with public notice directive
February 09, 2024 B-2-1 CONFIDENTIAL - Letter dated February 9, 2024 – BC Hydro submitting evidentiary update and compliance with public notice directive
March 18, 2024 B-3 Letter dated March 18, 2024 – BC Hydro submitting extension request for responses to BCUC and Intervener Information Requests No. 1

C Exhibits - Intervener Documents



Date Title Document Description
February 16, 2024 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated February 16, 2024 Request to Intervene by Thomas Hackney
March 08, 2024 C1-2 Letter dated March 8, 2024 – BCSEA submitting Information Request No. 1 to BC Hydro
February 19, 2024 C2-1 GITGA’AT FIRST NATIONS (GFN) - Letter dated February 19, 2024 Request to Intervene by David Benton
March 06, 2024 C2-2 Letter dated March 6, 2024 – GFN submitting Information Request No. 1 to BC Hydro
February 20, 2024 C3-1 NUXALK NATION - Letter dated February 20, 2024 Request to Intervene by Terry Webber
March 08, 2024 C3-2 Letter dated March 8, 2024 – Nuxalk Nation submitting Information Request No. 1 to BC Hydro
February 21, 2024 C4-1 HEILTSUK NATION - Letter dated February 21, 2024 Request to Intervene by Medric (Bo) Reid
March 08, 2024 C4-2 Letter dated March 8, 2024 – Heiltsuk Nation submitting Information Request No. 1 to BC Hydro
February 21, 2024 C5-1 YU KA WHU'TEN FORESTRY - Letter dated February 21, 2024 Request to Intervene by Stephen James
February 21, 2024 C6-1 ZONE II RATEPAYERS GROUP (ZONEII RPG) – Letter dated February 21, 2024 request to intervene by Sebastian Ennis, Iris Legal Law Corporation representing together Kwadacha Nation and Tsay Keh Dene Nation
March 08, 2024 C6-2 Letter dated March 8, 2024 – ZoneII RPG submitting Information Request No. 1 to BC Hydro