BC Hydro

Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022

Completed: 2022

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: December 17, 2021 @ 2:44 pm
G-26-22 Final Order with Reasons for Decision February 8, 2022

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
September 10, 2021 A-1 Letter dated September 10, 2021 – Appointing the Panel for the review of British Columbia Hydro and Power Authority Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022
October 01, 2021 A-2 Letter dated October 1, 2021 – BCUC Order G-287-21 establishing a regulatory timetable
October 15, 2021 A-3 Letter dated October 15, 2021 – BCUC Order G-299-21 establishing a further regulatory timetable
November 05, 2021 A-4 Letter dated November 5, 2021 – BCUC Information Request No. 1 to BC Hydro
November 05, 2021 A-5 CONFIDENTIAL - Letter dated November 5, 2021 – BCUC Confidential Information Request No. 1 to BC Hydro
November 09, 2021 A-6 Letter dated November 9, 2021 – BCUC Order G-327-21 amending the regulatory timetable

B Exhibits - Applicant Documents

Date Title Document Description
August 31, 2021 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated August 31, 2021 submitting Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022
August 31, 2021 B-1-1 CONFIDENTIAL - BC Hydro submitting Application for Mandatory Reliability Standards Costs Regulatory Account for Fiscal 2022 dated August 31, 2021
October 06, 2021 B-2 CONFIDENTIAL – Letter dated October 6, 2021 - BC Hydro submitting documents to be referenced in the in-camera session
November 08, 2021 B-3 Letter dated November 8, 2021 - BC Hydro submitting request to amend regulatory timetable
November 26, 2021 B-4 Letter dated November 26, 2021 - BC Hydro submitting responses to BCUC Information Request No. 1
November 26, 2021 B-4-1 CONFIDENTIAL - Letter dated November 26, 2021 - BC Hydro submitting confidential responses to BCUC Information Request No. 1
November 26, 2021 B-5 CONFIDENTIAL - Letter dated November 26, 2021 - BC Hydro submitting responses to BCUC Confidential Information Request No. 1
December 17, 2021 B-6 Letter dated December 17, 2021 - BC Hydro submitting response to Letters of Comment

Transcripts

Date Title Document Description
October 07, 2021 Transcript Volume 1a Confidential In-camera Session October 7, 2021

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more