BC Utilities Commission

Review of Thermal Energy Systems Regulatory Framework Guidelines - Phase 1

In Progress

Click Here for Phase 2

The BCUC has undertaken a review of the Thermal Energy Systems (TES) Regulatory Framework Guidelines, issued in 2015, which explain the current exemptions and address regulatory processes for all TES such as registration, complaints and reporting. Phase 1 of the Review of the TES Guidelines consists of a review of the exemptions granted to certain classes of TES from aspects of BCUC regulation.

Timetable

Subject Date
Pending ministerial approval TBD

Hearing and Other Documents

Title Document Description
Exhibit List Updated: January 30, 2024 @ 9:50 am
Panel Report Panel Report December 21, 2023

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
September 20, 2019 A-1 Letter dated September 20, 2019 - Appointing the Panel for the Review of Thermal Energy Systems Regulatory Framework Guidelines
December 20, 2019 A-2 Letter dated December 20, 2019 – BCUC Order G-341-19 Establishing a Public Hearing and Regulatory Timetable
January 15, 2020 A-3 Letter dated January 15, 2020 – Information regarding the BCUC Review of TES Guidelines
January 23, 2020 A-4 Letter dated January 23, 2020 – Additional information sheet regarding Thermal Energy Systems
March 03, 2020 A-5 Letter dated March 3, 2020 – BCUC requesting clarification on BCSEA submission on draft Terms of Reference
March 03, 2020 A-6 Letter dated March 3, 2020 – BCUC requesting clarification on Flintoff submission on draft Terms of Reference
March 09, 2020 A-7 Letter dated March 9, 2020 – BCUC submitting Terms of Reference
March 16, 2020 A-8 Letter dated March 16, 2020 – BCUC Order G-53-20 amending the Regulatory Timetable
March 19, 2020 A-9 Letter dated March 19, 2020 – Posting of Stream A Thermal Energy Systems Applications Extension
April 22, 2020 A-10 Letter dated April 22, 2020 – BCUC Order G-91-20 amending the Regulatory Timetable
April 22, 2020 A-11 Letter dated April 22, 2020 – BCUC providing Information on Workshop
April 22, 2020 A-11-1 Letter dated April 22, 2020 – BCUC providing Information on Workshop and updated Terms of Reference
November 02, 2020 A-11-2 Letter dated November 2, 2020 – BCUC providing information on December Workshop and Registration
May 08, 2020 A-12 Letter dated May 8, 2020 – BCUC response to Onni on confidentiality request
May 27, 2020 A-13 Letter dated May 27, 2020 – BCUC Order G-124-20 approving confidentiality request
May 27, 2020 A-14 Letter dated May 27, 2020 – BCUC submission on confidentiality requests and updated Terms of Reference
July 31, 2020 A-15 Letter dated July 31, 2020 – BCUC Letter cancelling Workshop
September 21, 2020 A-16 Letter dated September 21, 2020 – BCUC issuing clarification on the Regulatory Timetable
October 15, 2020 A-17 Letter dated October 15, 2020 – BCUC Order G-259-20 establishing a regulatory timetable
November 27, 2020 A-18 Letter dated November 27, 2020 – BCUC response to Creative Energy submission Exhibit C6-4
December 07, 2020 A-19 Letter dated December 7, 2020 – BCUC issuing guidance on workshop submissions
December 09, 2020 A-20 Letter dated December 9, 2020 – BCUC workshop presentation slides
December 11, 2020 A-21 Letter dated December 11, 2020 – BCUC letter on Written Submissions
December 18, 2020 A-22 Letter dated December 18, 2020 – BCUC Order G-341-20 amending the regulatory timetable
January 26, 2021 A-23 Letter dated January 26, 2021 – BCUC information on Further Process
March 31, 2021 A-24 Letter dated March 31, 2021 – BCUC update on further process
May 28, 2021 A-25 Letter dated May 28, 2021 – BCUC update on further process
August 25, 2021 A-26 Letter dated August 25, 2021 – BCUC update on further process
October 29, 2021 A-27 Letter dated October 29, 2021 – BCUC update on further process
January 26, 2022 A-28 Letter dated January 26, 2022 – BCUC request for submissions on draft framework
March 24, 2022 A-29 Letter dated March 24, 2022 – BCUC letter with amended regulatory timetable
April 28, 2022 A-30 Letter dated April 28, 2022 - BCUC response to BCOAPO extension request to file Final Argument
August 12, 2022 A-31 Letter dated August 12, 2022 – BCUC request for submissions
September 29, 2022 A-32 Letter dated September 29, 2022 – BCUC request for submissions
October 19, 2022 A-33 Letter dated October 19, 2022 – BCUC response to Borealis extension request and amending regulatory timetable
May 04, 2023 A-34 Letter dated May 4, 2023 – BCUC request for submissions
June 13, 2023 A-35 Letter dated June 13, 2023 – BCUC approval of Intervener Request from Tony Gioventu on behalf of CHOA-BC with subjects
September 28, 2023 A-36 Letter dated September 28, 2023 – BCUC amending the panel for the review of the TES Regulatory Framework Guidelines
October 18, 2023 A-37 Letter dated October 18, 2023 – BCUC request for submissions regarding Participant Assistance Cost Awards
December 21, 2023 A-38 Letter dated December 21, 2023 – BCUC issuing Panel Report
January 30, 2024 A-39 Letter dated January 30, 2024 – BCUC amending the panel for the review of the TES Regulatory Framework Guidelines
May 28, 2020 A2-1 Letter dated May 28, 2020 – BCUC staff submitting Stream A applications
December 08, 2020 A2-2 Letter dated December 8, 2020 – BCUC staff submitting Stream A applications

C Exhibits - Intervener Documents

BOREALIS GEOPOWER INC. (BOREALIS) – Letter dated January 22, 2020 request for Intervener Status by Alison Thompson
FORTISBC ALTERNATIVE ENERGY SERVICES INC. (FAES) – Letter dated January 23, 2020 request for Intervener Status by Grant Bierlmeier
MOVEMENT OF UNITED PROFESSIONALS (MOVEUP) – Letter dated January 23, 2020 request for Intervener Status by Jim Quail
BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) – Letter dated January 27, 2020 request for Intervener Status by Thomas Hackney and William Andrews
CITY OF ABBOTSFORD (ABBOTSFORD) – Letter dated January 27, 2020 request for Intervener Status by Aniz Alani
CREATIVE ENERGY VANCOUVER PLATFORMS INC. (CREATIVE ENERGY) – Letter dated January 29, 2020 request for Intervener Status by Rob Gorter
FORTISBC ENERGY INC. (FEI) – Letter dated January 27, 2020 request for Intervener Status by Doug Slater
FVB ENERGY INC. (FVB ENERGY) – Letter dated January 30, 2020 request for Intervener Status by Jim Manson
RIVER DISTRICT ENERGY (RDE) – Letter dated January 30, 2020 request for Intervener Status by Ross Hanson
BC OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, DISABILITY ALLIANCE BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY, KNOWN COLLECTIVELY IN REGULATORY PROCESSES AS “BCOAPO ET AL.” (BCOAPO ET AL) - Letter dated January 31, 2020 - Request for Intervener Status by Leigha Worth and Irina Mis
CORIX MULTI-UTILITY SERVICES INC. (CORIX) – Letter dated January 31, 2020 request for Intervener Status by Errol South
ONNI GROUP (ONNI) – Letter dated January 31, 2020 request for Intervener Status by Michelle McLarty
SSL-SUSTAINABLE SERVICE LTD. (SSL) – Letter dated January 31, 2020 request for Intervener Status by Lisa Parkes
FINK MACHINE INC. (FINK) – Submission dated November 23, 2020 Request for Late Intervener Status by David Dubois
RESIDENTIAL CONSUMER INTERVENOR GROUP (RCIG) – Submission dated January 22, 2021 Request for Late Intervener Status by Fredrick Ambrosson of Midgard Consulting Incorporated
CONDOMINIUM HOME OWNERS ASSOCIATION (CHOA-BC) – Letter dated June 7, 2023 request for Intervener Status by Tony Gioventu


Date Title Document Description
January 22, 2020 C1-1 BOREALIS GEOPOWER INC. (BOREALIS) – Letter dated January 22, 2020 request for Intervener Status by Alison Thompson
September 18, 2020 C1-2 Letter dated September 18, 2020 – Borealis submission on Terms of Reference and Scope
December 17, 2020 C1-3 Letter dated December 17, 2020 – Borealis submission on Terms of Reference
December 22, 2020 C1-4 Letter dated December 22, 2020 – Borealis submission on further process and intent to file Intervener Evidence
January 07, 2021 C1-5 Letter dated January 7, 2021 – Borealis Supplemental Written Submission
March 28, 2022 C1-6 Letter dated March 28, 2022 – Borealis Reply Written Submission
May 31, 2022 C1-7 Letter dated May 31, 2022 – Borealis reply comment on Draft Framework Guidelines
October 18, 2022 C1-8 Letter dated October 18, 2021 – Borealis submitting timetable extension request
October 27, 2022 C1-9 Letter dated October 27, 2022 – Borealis submission on proposal
November 16, 2022 C1-10 Letter dated November 16, 2022 – Borealis reply comments on Questions
October 24, 2023 C1-11 Letter dated October 24, 2023 – Borealis submission regarding Participant Assistance Cost Awards
January 23, 2020 C2-1 FORTISBC ALTERNATIVE ENERGY SERVICES INC. (FAES) – Letter dated January 23, 2020 request for Intervener Status by Grant Bierlmeier
February 12, 2020 C2-2 Letter dated February 12, 2020 – FAES submission on draft Terms of Reference
March 12, 2020 C2-3 Letter dated March 12, 2020 – FAES submitting response on Exhibit A-7
April 16, 2020 C2-4 Letter dated April 16, 2020 – FAES submission regarding request for confidentiality on Stream A TES Application
December 17, 2020 C2-5 Letter dated December 17, 2020 – FAES submission on Terms of Reference
January 14, 2021 C2-6 Letter dated January 14, 2021 – FAES submission on further process
April 28, 2022 C2-7 Letter dated April 28, 2022 – FAES comment on Draft Framework
May 31, 2022 C2-8 Letter dated May 31, 2022 – FAES reply comment on Draft Framework Guidelines
August 30, 2022 C2-9 Letter dated August 30, 2022 – FAES submission on proposal
October 27, 2022 C2-10 Letter dated October 27, 2022 – FAES submission on proposal
November 16, 2022 C2-11 Letter dated November 16, 2022 – FAES reply submission on proposal
May 25, 2023 C2-12 Letter dated May 25, 2023 – FAES submission regarding Strata TES Exemption
June 15, 2023 C2-13 Letter dated June 15, 2023 – FAES reply submission regarding Strata TES Exemption
October 27, 2023 C2-14 Letter dated October 26, 2023 – FAES submission regarding Participant Assistance Cost Awards
January 23, 2020 C3-1 MOVEMENT OF UNITED PROFESSIONALS (MOVEUP) – Letter dated January 23, 2020 request for Intervener Status by Jim Quail
January 27, 2020 C4-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) – Letter dated January 27, 2020 request for Intervener Status by Thomas Hackney and William Andrews
February 14, 2020 C4-2 Letter dated February 14, 2020 – BCSEA submission on draft Terms of Reference
March 05, 2020 C4-3 Letter dated March 5, 2020 – BCSEA response to BCUC request for clarification on draft Terms of Reference
March 18, 2020 C4-4 Letter dated March 18, 2020 – BCSEA response on FAES Exhibit C2-3
December 17, 2020 C4-5 Letter dated December 17, 2020 – BCSEA submission on scope
January 14, 2021 C4-6 Letter dated January 14, 2021 – BCSEA submission on further process
April 28, 2022 C4-7 Letter dated April 28, 2022 – BCSEA comments on Draft Framework
May 31, 2022 C4-8 Letter dated May 31, 2022 – BCSEA reply comments on Draft Framework Guidelines
September 01, 2022 C4-9 Letter dated September 1, 2022 – BCSEA submission on proposal
September 15, 2022 C4-10 Letter dated September 15, 2022 – BCSEA providing reply submission on Exhibit A-31
October 27, 2022 C4-11 Letter dated October 27, 2022 – BCSEA submission on proposal
November 10, 2022 C4-12 Letter dated November 10, 2022 – BCSEA submitting reply comments on Low Carbon questions
May 25, 2023 C4-13 Letter dated May 25, 2023 – BCSEA submission regarding Strata TES Exemption
June 15, 2023 C4-14 Letter dated June 15, 2023 – BCSEA reply submission regarding Strata TES Exemption
October 03, 2023 C4-15 Letter dated October 3, 2023 – BCSEA submission regarding Participant Assistance Cost Award
October 20, 2023 C4-16 Letter dated October 20, 2023 – BCSEA submission regarding Participant Assistance Cost Awards
November 02, 2023 C4-17 Letter dated November 2, 2023 – BCSEA no reply submission regarding Participant Assistance Cost Awards
January 27, 2020 C5-1 CITY OF ABBOTSFORD (ABBOTSFORD) – Letter dated January 27, 2020 request for Intervener Status by Aniz Alani
February 14, 2020 C5-2 Letter dated February 14, 2020 – Abbotsford submission on draft Terms of Reference
January 29, 2020 C6-1 CREATIVE ENERGY VANCOUVER PLATFORMS INC. (CREATIVE ENERGY) – Letter dated January 29, 2020 request for Intervener Status by Rob Gorter
February 13, 2020 C6-2 Letter dated February 13, 2020 – Creative Energy submission on draft Terms of Reference
April 16, 2020 C6-3 Letter dated April 16, 2020 – Creative Energy submission to Exhibit A-9
November 13, 2020 C6-4 Letter dated November 13, 2020 – Creative Energy submission regarding Preparation for Workshop
December 09, 2020 C6-5 Letter dated December 9, 2020 – Creative Energy submitting Workshop Slides
December 14, 2020 C6-6 Letter dated December 14, 2020 - Creative Energy submitting reply to Exhibit A-21
December 17, 2020 C6-7 Letter dated December 17, 2020 – Creative Energy Written submission on Terms of Reference
January 14, 2021 C6-8 Letter dated January 14, 2021 – Creative Energy submission on further process
March 24, 2022 C6-9 Letter dated March 24, 2022 – Creative Energy submitting extension request to file written submission
April 26, 2022 C6-10 Letter dated April 26, 2022 – Creative Energy submission on Draft Document and Proposed TES Exemptions
May 31, 2022 C6-11 Letter dated May 31, 2022 – Creative Energy reply comment on Draft Framework Guidelines
September 01, 2022 C6-12 Letter dated September 1, 2022 – Creative Energy submission on proposal
October 27, 2022 C6-13 Letter dated October 27, 2022 – Creative Energy reply submission on Exhibit A-32
January 27, 2020 C7-1 FORTISBC ENERGY INC. (FEI) – Letter dated January 27, 2020 request for Intervener Status by Doug Slater
February 12, 2020 C7-2 Letter dated February 12, 2020 – FEI submission on draft Terms of Reference
April 28, 2022 C7-3 Letter dated April 28, 2022 – FEI comment on Draft Framework
May 31, 2022 C7-4 Letter dated May 31, 2022 – FEI reply comment on Draft Framework Guidelines
August 30, 2022 C7-5 Letter dated August 30, 2022 – FEI submission on proposal
October 27, 2022 C7-6 Letter dated October 27, 2022 – FEI submission on proposal
November 16, 2022 C7-7 Letter dated November 16, 2022 – FEI reply submission on proposal
May 25, 2023 C7-8 Letter dated May 25, 2023 – FEI submission regarding Strata TES Exemption
June 15, 2023 C7-9 Letter dated June 15, 2023 – FEI reply submission regarding Strata TES Exemption
October 27, 2023 C7-10 Letter dated October 26, 2023 – FEI submission regarding Participant Assistance Cost Awards
January 30, 2020 C8-1 FVB ENERGY INC. (FVB ENERGY) – Letter dated January 30, 2020 request for Intervener Status by Jim Manson
January 30, 2020 C9-1 RIVER DISTRICT ENERGY (RDE) – Letter dated January 30, 2020 request for Intervener Status by Ross Hanson
April 28, 2022 C9-2 Letter dated April 28, 2022 – RDE comment on Draft Framework
May 31, 2022 C9-3 Letter dated May 31, 2022 – RDE reply comment on Draft Framework Guidelines
November 17, 2022 C9-4 Letter dated November 17, 2022 – RDE reply comments on Low Carbon Definitions
May 25, 2023 C9-5 Letter dated May 25, 2023 – RDE submission regarding Strata TES Exemption
January 31, 2020 C10-1 BC OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, DISABILITY ALLIANCE BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY, KNOWN COLLECTIVELY IN REGULATORY PROCESSES AS “BCOAPO ET AL.” (BCOAPO ET AL) - Letter dated January 31, 2020 - Request for Intervener Status by Leigha Worth and Irina Mis
February 14, 2020 C10-2 Letter dated February 14, 2020 – BCOAPO submission on draft Terms of Reference
December 16, 2020 C10-3 Letter dated December 16, 2020 – BCOAPO submitting extension request
January 14, 2021 C10-4 Letter dated January 14, 2021 – BCOAPO submission on further process
April 28, 2022 C10-5 Letter dated April 28, 2022 – BCOAPO submitting extension request to file Final Argument
May 31, 2022 C10-6 Letter dated May 31, 2022 – BCOAPO reply comment on Draft Framework Guidelines
September 01, 2022 C10-7 Letter dated September 1, 2022 – BCOAPO submission on proposal
September 15, 2022 C10-8 Letter dated September 15, 2022 – BCOAPO providing reply submission on Exhibit A-31
October 27, 2022 C10-9 Letter dated October 27, 2022 – BCOAPO providing reply submission on Exhibit A-32
May 25, 2023 C10-10 Letter dated May 25, 2023 – BCOAPO submission regarding Strata TES Exemption
October 27, 2023 C10-11 Letter dated October 26, 2023 – BCOAPO submission regarding Participant Assistance Cost Awards
January 31, 2020 C11-1 CORIX MULTI-UTILITY SERVICES INC. (CORIX) – Letter dated January 31, 2020 request for Intervener Status by Errol South
February 07, 2020 C11-2 Letter dated February 7, 2020 – Corix submission on draft Terms of Reference
December 17, 2020 C11-3 Letter dated December 17, 2020 – Corix submission on Terms of Reference
January 12, 2021 C11-4 Letter dated January 12, 2021 – Corix submission on further process
April 28, 2022 C11-5 Letter dated April 28, 2022 – Corix comments on Draft Framework
May 31, 2022 C11-6 Letter dated May 31, 2022 – Corix reply comment on Draft Framework Guidelines
August 31, 2022 C11-7 Letter dated August 31, 2022 – Corix submission on proposal
October 27, 2022 C11-8 Letter dated October 27, 2022 – Corix providing reply submission on Exhibit A-32
January 31, 2020 C12-1 ONNI GROUP (ONNI) – Letter dated January 31, 2020 request for Intervener Status by Michelle McLarty
March 19, 2020 C12-2 Letter dated March 19, 2020 – Onni submission on application
April 14, 2020 C12-3 Letter dated April 14, 2020 – Onni submission regarding request for confidentiality on Stream A TES Application
May 11, 2020 C12-4 Letter dated May 11, 2020 – Onni submitting confirmation Disclosure Statement has been filed
December 17, 2020 C12-5 Letter dated December 17, 2020 – Onni submission on Terms of Reference
January 31, 2020 C13-1 SSL-SUSTAINABLE SERVICE LTD. (SSL) – Letter dated January 31, 2020 request for Intervener Status by Lisa Parkes
December 17, 2020 C13-2 Letter dated December 17, 2020 – SSL submission on Terms of Reference
January 14, 2021 C13-3 Letter dated January 14, 2021 – SSL submission on further process
November 23, 2020 C14-1 FINK MACHINE INC. (FINK) – Submission dated November 23, 2020 Request for Late Intervener Status by David Dubois
December 09, 2020 C14-2 Letter dated December 9, 2020 – Fink submitting Workshop Slides
January 14, 2021 C14-3 Letter dated January 14, 2021 – Fink submission on further process
January 22, 2021 C15-1 RESIDENTIAL CONSUMER INTERVENOR GROUP (RCIG) – Submission dated January 22, 2021 Request for Late Intervener Status by Fredrick Ambrosson of Midgard Consulting Incorporated
April 28, 2022 C15-2 Letter dated April 28, 2022 – RCIA providing no submission on Draft Framework
May 31, 2022 C15-3 Letter dated May 31, 2022 – RCIA reply comment on Draft Framework Guidelines
August 30, 2022 C15-4 Letter dated August 30, 2022 – RCIA submission on proposal
September 15, 2022 C15-5 Letter dated September 15, 2022 – RCIA providing reply submission on Exhibit A-31
October 20, 2022 C15-6 Letter dated October 20, 2022 – RCIA providing reply submission on Exhibit A-32
November 08, 2022 C15-7 Letter dated November 8, 2022 – RCIA providing reply submission on questions
May 25, 2023 C15-8 Letter dated May 25, 2023 – RCIA submission regarding Strata TES Exemption
June 29, 2023 C15-8-1 Letter dated June 29, 2023 – RCIA submitting errata to reply submission
June 14, 2023 C15-9 Letter dated June 14, 2023 – RCIA reply submission regarding Strata TES Exemption
October 26, 2023 C15-10 Letter dated October 26, 2023 – RCIA submission regarding Participant Assistance Cost Awards
November 02, 2023 C15-11 Letter dated November 2, 2023 – RCIA reply submission regarding Participant Assistance Cost Awards
June 07, 2023 C16-1 CONDOMINIUM HOME OWNERS ASSOCIATION (CHOA-BC) – Letter dated June 7, 2023 request for Intervener Status by Tony Gioventu

D Exhibits — Interested Party Documents

Date Title Document Description
January 20, 2020 D-1 REMOVED NOW INTERVENER C13-1
January 20, 2020 D-2 CITY OF TERRACE (TERRACE) – Submission dated January 20, 2020 Request for Interested Party Status by Deklan Corstanje
January 20, 2020 D-3 KERR WOOD LEIDAL ASSOCIATES (KWLA) – Submission dated January 20, 2020 Request for Interested Party Status by Ayman Fahmy
January 23, 2020 D-4 AMERESCO CANADA LTD. (AMERESCO) - Submission dated January 23, 2020 Request for Interested Party Status by Doug Wall
January 29, 2020 D-5 CITY OF SURREY (SURREY) – Submission dated January 29, 2020 Request for Interested Party Status by Cindy Picard
January 29, 2020 D-6 CITY OF BURNABY (BURNABY) – Submission dated January 29, 2020 Request for Interested Party Status by James Lota
January 30, 2020 D-7 LULU ISLAND ENERGY CORPORATION LTD. (LULU ISLAND) – Submission dated January 30, 2020 Request for Interested Party Status by Brendan Burns
January 31, 2020 D-8 TECHNICAL SAFETY BC (TSBC) – Submission dated January 31, 2020 Request for Interested Party Status by Rick Vanier
January 31, 2020 D-9 DISTRICT OF KITIMAT (KITIMAT) – Submission dated January 31, 2020 Request for Interested Party Status by Warren Waycheshen
February 04, 2020 D-10 REGIONAL DISTRICT OF CENTRAL KOOTENAY (RDCK) – Submission dated February 4, 2020 Request for Interested Party Status by Paris Smith
February 11, 2020 D-11 FLINTOFF, D. (FLINTOFF)- Email dated February 11, 2020 Request for Interested Party Status
February 14, 2020 D-11-1 Letter dated February 14, 2020 – Flintoff submission on draft Terms of Reference
March 05, 2020 D-11-2 Letter dated March 5, 2020 – Flintoff response to BCUC request for clarification on submission on draft Terms of Reference
March 13, 2020 D-11-3 Letter dated March 13, 2020 – Flintoff submitting responses on Exhibit A-7
September 01, 2022 D-11-4 Letter dated September 1, 2022 – Flintoff submission on proposal
October 20, 2023 D-11-5 Letter dated October 20, 2023 – Flintoff submission regarding Participant Assistance Cost Awards
November 02, 2023 D-11-6 Letter dated November 2, 2023 – Flintoff no reply submission regarding Participant Assistance Cost Awards
March 02, 2020 D-12 QMC – Submission dated March 2, 2020 Request for Interested Party Status by James Easton
March 10, 2020 D-13 FENIX ENERGY (FENIX ENERGY) – Submission dated March 10, 2020 Request for Interested Party Status by Alexandre Moor
December 17, 2020 D-13-1 Letter dated December 17, 2020 – Fenix Energy submission on Terms of Reference
November 03, 2021 D-14 UNIVERSITY OF BRITISH COLUMBIA (UBC) - Submission dated November 3, 2021 Request for Interested Party Status by Joshua Wauthy
January 29, 2022 D-15 CURRY, J. (CURRY) - Submission dated January 29, 2022 Request for Interested Party Status
November 28, 2022 D-16 BROID, D. (BROID) - Submission dated November 28, 2022 Request for Interested Party Status

Transcripts

Date Title Document Description
December 09, 2020 Transcript Volume 1 Web-based Workshop December 9, 2020

Receive Web Notifications

Subscribe to a proceeding to receive email notifications when public documents are added to this proceeding.

Subscribe here